Why the proofing cycle can be compressed
The sample center splits the proofing into two stages: those that can be processed with existing blanks will go through the CNC fast track; those that require new structures will still go through the mold process. Most of the changes in the size of the conventional interface between the gun and the single-board computer shell fall in the first paragraph. Weijiaxin used stock aluminum blocks and universal fixtures to go directly to the machine, and programmed to change the size according to the parameterized template, saving the time of mold opening and mold testing.
The channel time is calculated on working days, from drawing confirmation to sample sending, which is much shorter than the complete mold opening process. Changes that can be processed include overall dimensions, interface window positions, stud positions and surface treatment colors; for major changes involving parting surfaces and internal stiffener directions, it is still recommended to open the mold for verification.
What can and cannot be verified by quick prototyping?
CNC prototyping can verify the assembly relationship, interface alignment, sealing ring compression amount and overall machine appearance ratio, and can also be installed on boards for power-on testing. It cannot replace die castings to verify wall thickness uniformity and internal pores, nor does it reflect mold life and batch consistency. This will be explained when sending samples to avoid accepting quick samples as mass production parts.
The sample comes with a dimensional report and material description, and the key matching dimensions are marked with actual measured values. After the customer gets the sample and finds assembly interference, he can directly mark the modifications on the drawing, and the next round of proofing will be redone according to the new drawing.
Fast lanes also have capacity boundaries. Urgent items submitted collectively at the same time need to be queued, and the processing time for samples involving special alloys or thick-walled structures is also longer than for regular items. Explain the purpose and verification focus before submission, and the sample center will give a feasible delivery time based on priority.
Implications for production scheduling in the verification stage
In the early stage of the project, the biggest fear is to open the mold before the structure is determined. Quick prototyping allows structural verification and mold preparation to be carried out in parallel: the client prepares for complete machine assembly and inspection, while Weijiaxin advances the mold plan simultaneously, without waiting for each other.
- Small changes such as size, window opening, and color changes are made through the CNC channel;
- After the structure is finalized, the mold is opened, and the sample data is used as the input for mold review;
- Small batch orders can be fine-tuned with existing molds on the basis of quick samples;
- Samples and mass-produced parts are marked separately, and the acceptance standards are clearly defined.
After the channel is opened, sample sending and mold making no longer compete for the same batch of engineering resources. The sample center arranges production independently, and urgent items are processed in the order of submission. Customers can get the sample delivery time in advance.