Where is the cycle spent?
The time from drawing to batch shipment of the shell is usually distributed in several stages: mold design and production, mold trial and sample confirmation, die-casting and post-processing, surface treatment, inspection and packaging. The time that actually occupies the machine tool is limited, and more waiting occurs in queuing, transfer and information confirmation between processes. If you want to shorten the cycle, the focus is to compress these non-processing times. A revision often brings about mold modifications, sample redoing, and batch rearrangement. When these three stages are superimposed, the cycle time exceeds expectations.
Weijiaxin started in Shiyan, Baoan, Shenzhen in 2009, and later set up a production base in Tangxia, Dongguan. Molds, die-casting, CNC and surface treatment are all completed within its own system. The two places operate according to the same set of process documents and inspection standards, and processes can be transferred within the system without queuing up for a certain link. Transfers between the two places are scheduled on a fixed schedule, reducing the need to wait for temporary transportation.
Collaboration relies on the same caliber
The most common problem in cross-base collaboration is not the equipment, but inconsistent standards: for the same drawing, if the tolerances and appearance judgments read out by the two places are different, the samples will be returned repeatedly. The method is to write the key dimensions, sealing surface requirements, film thickness and color difference determination into a common document. The first item is confirmed by both places, and then each fills in the same record form. Weijiaxin placed this shared document in the same location in the review directories of both places, and version updates were pushed simultaneously.
The transfer of semi-finished products needs to be traceable. Each batch comes with a transfer card, indicating the completed process, inspection conclusion and remaining balance; the quantity and appearance are handed over before transfer to avoid collisions being discovered in the next process, making it difficult to define responsibilities and rework. The handover record is signed by both parties, so that there are well-documented records in case of disputes.
A little trade-off in production scheduling
It is normal for batch orders and sample orders to grab the same batch of equipment. Arrange proofing and mold testing in the gap between batch production and use fixed time windows to process them, so that small orders will not be delayed indefinitely and the batch rhythm will not be interrupted. Equipment maintenance takes up as much time as mold changing. Scheduling maintenance between orders is more controllable than shutting down the line afterward. Information synchronization on the customer side is also indispensable: mold progress, mold trial results, and batch start time are fed back by nodes, allowing customers to arrange their own assembly plans.
- Unify the drawing caliber and appearance judgment standards to reduce cross-base re-inspections;
- Concentrate key processes in one place to reduce the round trip of semi-finished products;
- Semi-finished products are transferred with circulation cards, and quantity and appearance are handed over on the spot;
- Set a fixed time window for proofing to avoid crowding with batches.
For customers, the value of dual bases is not in scale, but in that processes do not need to be outsourced and exceptions can be closed internally. Cycle time reduction comes from one less wait, not one more device.