Let’s first set the caliber clearly
The most common area of dispute when delivering a review is the caliber. Whether the delivery date is calculated based on the order confirmation date or the drawing freezing date, and whether the first-time pass rate is calculated as the parts that pass re-inspection after return for repair, the two sentences are different, and the conclusion can be very different. The method is to write the caliber in one line before the review and attach it to the footer of the data table. All departments will read the same definition.
The delivery date is set when the entire batch is put into storage, not the last one off the assembly line. The first pass rate is calculated by dividing the number of pieces that passed the first inspection by the number of input pieces. Those that pass after repair are counted separately and are not included in the first pass. Only after the caliber is fixed can the monthly figures be comparable, and improvement actions can be directed to specific processes.
Deviations are concentrated in three categories of links
The review classified the deviations into three categories according to their sources: incoming materials and mold status, processing and surface treatment, assembly and packaging. The first type is manifested in out-of-tolerance dimensions and appearance color differences, the second type is concentrated in spraying rework and time-consuming adjustments, and the third type mostly occurs in missing parts and mislabeling. Categorization makes responsibilities clear so improvements don’t have to wait until next month.
The most direct impact on delivery time is often not the working hours of a single piece, but waiting. Mold repair, workpiece inspection, surface treatment and wiring of semi-finished products, etc., these waits are not conspicuous between processes, but cumulatively account for a considerable proportion. When reviewing, list the waiting time of each batch in a separate column, which makes it easier to find the entrance than just looking at the total period.
The focus on the customer side is more direct: whether the goods can arrive on the promised date, and whether they can be assembled directly online after arrival. Therefore, the internal review should not only look at the output and working hours, but also the on-time rate of the entire batch being put into storage, and the number of pieces picked out for repair on the assembly line. Only by looking at the two items together can we judge whether the improvement in delivery time has come at the expense of quality.
Improvement actions must be carried out at the post
- Confirmation of the first piece of key parts is completed in advance before work, reducing the rework of the entire batch;
- Surface treatment is grouped and arranged according to color to shorten the time for color change and cleaning;
- Safety inventory is set up for commonly used accessories, and the list is checked twice before packaging;
- A short meeting is held once a week, and only three issues that have not been closed are resolved.
Review is not to find an explanation for the numbers, but to make the next promise more reliable. Weijiaxin has fixed this mechanism into a monthly action. Delivery, quality and production sit together and look at the same table. The changes experienced by customers are more accurate delivery replies and fewer expediting calls.